IC4 Roof access IN KASTRUPWorks by railway lines |
|||
The turnkey contract is divided into 3 stages. Stages 2 and 3 have to be planned again as the columns have to be positioned differently on this side of the track. We must produce a total of 960 m grating walkway to be installed on approx. 144 columns.